Geography of work
- city of Moscow
- Republic Of Dagestan
- Republic Of North Ossetia
- Magadan region
- Republic Karachay-Cherkess
In August 2019, within the framework of the contract with «Dagestanskaya setevaya kompaniya» JSC, repair works of equipment at Kasumkentskih RES facilities were started for:
In August 2019,within the framework of the contract with «Dagestanskaya setevaya kompaniya» JSC, repair works on the 0.4 kV and 10/0. 4 kV overhead lines of the Ahtynskih RES electric grid complex were started.:
In 2018, work began on the construction of a garage building for the needs of JSC «Rusgidro Snabzhenie»
Implementation of works on creation of a loud-speaker notification system on Kaskade Sulakskih GES for the needs of the branch of PJSC «RusGidro» - «Dagestanskij filial»
Park improvements in the village of Levashi
Delivery of telecommunications equipment under the defense order for the Ministry of internal Affairs of the Republic of Dagestan.
In 2017, more than 35 thousand tons of cement were delivered to the construction site «Zaramagskie GES».
In the 4th quarter of 2016, major repairs were made to the sports hall with auxiliary facilities at the school in the village of Tukita, Khasavyurt district.
Work has been completed to strengthen the tsemzavesa CP-1, 2 and restore the piezometric and drainage network after strengthening at the Irganayskaya GES.
In 2016, work was completed and a 120-apartment residential building was commissioned for employees of the Ministry of emergency situations of Russia in the Republic of Dagestan.
In the 1st quarter of 2015, «Emergency repair work was performed on the roof of the administration building of the MO Gunibsky district»
In the 2nd quarter of 2015, road repairs were completed in the Gunib district.